Plaquemines LNG project granted request to commission & introduce hazardous fluids
On 21 November 2024, FERC granted Venture Global’s request to commission and introduce hazardous fluids into the first block of the Plaquemines LNG project. While each block of Plaquemines is quite small at 1.2mtpa, ramp-up time across all blocks was quite rapid in the case of Venture Global’s Calcasieu Pass LNG project. In 2022 Calcasieu Pass’ rate of cargo production reached ~7 cargoes per month within ~90 days of its first export.